PMP® Challenge Question – 10/15

From 9/15: What’s the difference between leadership and management?

The primary difference is that a manager is typically a person in authority while a leader is a person who accomplishes goals through influence. For a more detailed explanation, see The Practice of Leadership blog.

Now here’s a question for 11/1:

A contingency reserve is an amount of money set aside in the project budget based on the impact, probability, and expected monetary value of a risk event. A project has risks A and B. A has 25% probability of occurring and a negative impact of -$100,000while B has 45% probability of occurring and a negative impact of -$90,000. What is the expected monetary value (Ex$V) for the risk requiring the largest contingency?

Short URL: http://bit.ly/fCRU3A

Category: PMP® Challenge Question

Tagged: ,

Leave a Reply

Past Articles

Links and Buttons

Add to Technorati Favorites



Blogging Fusion Blog Directory

San Diego Blog News

Submit Express Inc.Submit Express - SEO Services

Disclaimer

All opinions on this blog are those of the site owner and do not reflect the opinion of any other entity. Information on this site may contain errors or inaccuracies; The Project Notebook does not make warranty as to the correctness or reliability of the site's content. If you believe something on this site is inappropriate and should be removed, please contact the site owner at sdcapmp at aol dot com.

Notices

"PMP" is a registered mark of the Project Management Institute.

Copyright

© 2010-2012 Ray W. Frohnhoefer, MBA, PMP, CCP