The Project Notebook

PMP® Challenge Question – 6/1

The question posed for today is “What does RACI stand for?”

RACI is a technique which can be used for creating a RAM or Responsibility Assignment Matrix. The letters stand for Responsible, Accountable, Consulted, and Informed. Some articles about RACI add “VS” for Verifies and Signs Off.

Well that one was easy!

Here’s a question for 6/15:

What do we call the narrative description of services to be supplied as part of a contract?

Check back on 6/15 for the answer!

Short URL: http://bit.ly/f4uZBh

Category: PMP® Challenge Question

Tagged: , ,

Leave a Reply

Past Articles

Links and Buttons

Add to Technorati Favorites



Blogging Fusion Blog Directory

San Diego Blog News

Submit Express Inc.Submit Express - SEO Services

Disclaimer

All opinions on this blog are those of the site owner and do not reflect the opinion of any other entity. Information on this site may contain errors or inaccuracies; The Project Notebook does not make warranty as to the correctness or reliability of the site's content. If you believe something on this site is inappropriate and should be removed, please contact the site owner at sdcapmp at aol dot com.

Notices

"PMP" is a registered mark of the Project Management Institute.

Copyright

© 2010-2012 Ray W. Frohnhoefer, MBA, PMP, CCP