The Project Notebook

PMP® Challenge Question – 2/1

There were no correct responses to the last challenge question, so I’ll hold those questions for future use. Here’s a fresh question to start off February:

An Earned Value Analysis for a recently closed out project revealed:

SPI = 0.7, CPI = 1.0

State at least THREE conclusions you can draw from this statement.

See you on 2/15 with the correct answer!

Short URL: http://bit.ly/dJ1hqW

Category: PMP® Challenge Question

Tagged: ,

One Response

  1. Cade Johnson says:

    The obvious conclusion you can draw from a schedule performance index of less than one is that the project is behind schedule. A cost performance index of 1.0 indicates that the project is exactly where it should be based on earned value vs actual costs. The last conclusion you could make would be that the estimate at completion is on track. Using the short BAC estimate you could conclude costs are on track for the your EAC.

Leave a Reply

Past Articles

Links and Buttons

Add to Technorati Favorites



Blogging Fusion Blog Directory

San Diego Blog News

Submit Express Inc.Submit Express - SEO Services

Disclaimer

All opinions on this blog are those of the site owner and do not reflect the opinion of any other entity. Information on this site may contain errors or inaccuracies; The Project Notebook does not make warranty as to the correctness or reliability of the site's content. If you believe something on this site is inappropriate and should be removed, please contact the site owner at sdcapmp at aol dot com.

Notices

"PMP" is a registered mark of the Project Management Institute.

Copyright

© 2010-2012 Ray W. Frohnhoefer, MBA, PMP, CCP