PMP® Challenge Question – 5/1

The 4/15 Challenge Question was:

Senior management and the project sponsor tell you the project needs to be brought in two days earlier than expected to meet an important deadline for a significant financial payment to your company. What steps should you take immediately?

Answer: Bring the project team together for a special meeting to look at possibilities of applying crashing or fast-tracking to the schedule to bring it in by the required amount.

One way or the other, you need to let the project sponsor and senior management know.

So here’s the 5/1 Challenge Question:

Your team needs to solicit expert opinion to help identify the feasibility of the project and make sure the schedule is sound. Your organization has a lot of top notch people, but some of them tend to dominate discussions. What technique would you use to collect the necessary information without allowing one expert to dominate the discussion?

See you May 15th! The Project Notebook will be starting a new giveaway with some new prizes, so be sure to visit!

Short URL: http://bit.ly/facL9q

Category: PMP® Challenge Question

Tagged:

Leave a Reply

Past Articles

Links and Buttons

Add to Technorati Favorites



Blogging Fusion Blog Directory

San Diego Blog News

Submit Express Inc.Submit Express - SEO Services

Disclaimer

All opinions on this blog are those of the site owner and do not reflect the opinion of any other entity. Information on this site may contain errors or inaccuracies; The Project Notebook does not make warranty as to the correctness or reliability of the site's content. If you believe something on this site is inappropriate and should be removed, please contact the site owner at sdcapmp at aol dot com.

Notices

"PMP" is a registered mark of the Project Management Institute.

Copyright

© 2010-2012 Ray W. Frohnhoefer, MBA, PMP, CCP