PMP Challenge Question – 9/1

It’s time for another challenge question and this one is built off the last one (8/15).

Assuming the Early Start of each task from 8/15 is the Optimistic Time, the Late Start Date is the Pessimistic Time,and the provided effort is the Most Likely Time, calculate the PERT time for the project network.

Weren’t able to complete the 8/15 Challenge but want to try this one? The solution can be found here!

Don’t forget to visit again next week, plus on 9/15 there will be another PMP Challenge Question. We’re also getting closer to the big PMP giveaway ….

What do you think of this post?
  • Awesome 
  • Interesting 
  • Useful 
  • Boring 
  • Sucks 

Category: PMP® Challenge Question

Tagged: ,

Leave a Reply

Past Articles

Links and Buttons

Add to Technorati Favorites



Blogging Fusion Blog Directory

San Diego Blog News

Submit Express Inc.Submit Express - SEO Services

Disclaimer

All opinions on this blog are those of the site owner and do not reflect the opinion of any other entity. Information on this site may contain errors or inaccuracies; The Project Notebook does not make warranty as to the correctness or reliability of the site's content. If you believe something on this site is inappropriate and should be removed, please contact the site owner at sdcapmp at aol dot com.

Notices

"PMP" is a registered mark of the Project Management Institute.

Copyright

© 2010-2012 Ray W. Frohnhoefer, MBA, PMP, CCP